Alok is a project manager for a development 

project which will last for one and half year and involves many stakeholders. 

How often he should risk identification take place?

Once at the beginning of the project
Once per each phase of the project
Throughout the build phase of the project
Throughout the project lifecycle
Verified Answer
Correct Option - d