At the end of the sixth sprint, the internal sponsors are not satisfied with the progress of the
product being built. The current state of the product is not as expected and will require additional sprints
and more budget than originally anticipated at the start of the project.
What factors may have led to this?

  1. The Product Owner has not been engaging with sponsors frequently enough and has not been kept aware of the overall progress of the project
  2. The sponsors haven’t been using sprint reviews to actively engage, and inspect and evaluate progress
  3. The stakeholders have not been using the Daily Scrum effectively to track the Development Team’s progress
  4. The Scrum Master has not ensured transparency

Options i), ii) & iii) only

Options i), ii) & iv) only

Options ii), iii) & iv) only

Options ii) & iii) only

Verified Answer
Correct Option - b

To get all Infosys Certified Expert in Agile coaching Exam questions Join Group https://bit.ly/infy_premium_group

We're passionate about offering best placement materials and courses!! A one stop place for Placement Materials. We daily post Offcampus updates and Placement Materials.

Qtr No. 213, New Town Yehlanka Indore 454775

admin@prepflix.in