Choose the option from the given choices which represent the activities that may done during product backlog refinement meeting.

 

A)Revisiting the product backlog for revised priorities

B)Planning for a sprint

C)Understanding stories for the next few sprints

D)Addition of new items to the product backlog based on customer feedback with a possible revisit of release date

E)Drawing the sprint burndown chart

F)Drawing the release burndown chart

Activities D, E, F only
Activities A, B, C, D only
Activities A, C, D only
All the given activities
Verified Answer
Correct Option - c