Match the following:

  1. Portfolio planning
  2. Product planning
  3. Release planning
  4. Iteration planning
  5. Daily planning

 

  1. Make economically good choices
  2. Identify routine activities
  3. Road map for development
  4. Identification of priority work
  5. Decide scope of delivery

A->1,B->3, C->5, D->4, E->2
A->1,B->2, C->3, D->4, E->5
A->3,B->5, C->2, D->1, E->4
A->5,B->3, C->1, D->4, E->2
Verified Answer
Correct Option - a