One of the strategies in risk response planning is mitigate 

the risk. Which of the followings explains the mitigate strategy

Shifting the negative impact of a threat, along with ownership of the response, to a third party
Changing the project management plan to eliminate the threat posed by an adverse risk,  to isolate the project objectives from the risk’s impact, or to relax the objective that is in jeopardy
Seeks to reduce the probability and/or impact of a threat to an acceptable threshold
None of the choices
Verified Answer
Correct Option - c