Planning procedure of 1 means

 Manual with Check. Planned order for header product will get created only if sufficient receipts for component are present to make the required qty of header product
 Manual without Check. Planned order for header product will get created irrespective of whether or not adequate component receipts are present
 There is no such planning procedure
 Planning in planning run. 1 is the default standard planning procedure to enable planning of products in planning run
Verified Answer
Correct Option - a