Please highlight the correct statement regarding PPDS horizons

 PPDS plans within the PPDS horizon and the planning time fence is ignored as it is relevant to SNP
 PPDS plans within the planning time fence but outside of the PPDS horizon
 PPDS Plans within the PPDS Horizon but does not plan before the planning time fence (PTF) as it is a frozen horizon. Planner can manually create receipts in PTF
 PPDS Plans within the PPDS Horizon but does not plan before the planning time fence (PTF) as it is a frozen horizon. Planner CANNOT manually create receipts in PTF as it is a frozen zone.
Verified Answer
Correct Option - c

To get all Infosys Certified SAP APO PPDS Professional Consultant Exam questions Join Telegram Group https://rebrand.ly/lex-telegram-236dee

Telegram