Project need to estimate the number of resources required for next month. The project has ticket arrival rate = 431 tickets /month, closure rate = 388 tickets / month, what model can they use to meet the current work load ?

Poisson distribution

SLA analytics model

Capacity planning model

iPPM (integrated prediction model)

Verified Answer
Correct Option - c