Project need to estimate the number of resources required for next month. The project has ticket arrival rate = 431 tickets /month, closure rate = 388 tickets / month, what model can they use to meet the current work load ?

Poisson distribution

SLA analytics model

Capacity planning model

iPPM (integrated prediction model)

Verified Answer
Correct Option - c

To get all Infosys Certified Quality Professional - Certification Exam questions Join Telegram Group https://rebrand.ly/lex-group-70b557

Telegram

We're passionate about offering best placement materials and courses!! A one stop place for Placement Materials. We daily post Offcampus updates and Placement Materials.

Qtr No. 213, New Town Yehlanka Indore 454775

admin@prepflix.in

Updated on Thu, 21 Aug 2025