Raj is a project manager for a production support project. 

A major risk that has been identified is key resource moving out of the project.

 As a strategy to respond to this risk, 

Raj along with team member prepared 

support process related documents. What type of risk response is Raj following?

Accept
Avoid
Mitigate
Transfer
Verified Answer
Correct Option - c