Select the correct statements:

A Sprint Backlog (SB):

[Choose 3 correct answers]

Is a list of all the requirements that the development team collectively commits to complete during a sprint

Is a list of all the requirements that the Product Owner requires to be done during a sprint

Is a list of all the requirements that the Scrum Master requires the development team to complete during a sprint

Once the work begins on iteration, Sprint Backlog doesn’t change

Verified Answer
Correct Option - adf