Team was in warranty phase for 2 applications and there were about 10 critical defects identified, it was observed by the PM that only 70% of test cases were covered during SIT phase due to critical delivery timelines, can you identify which practice area needs improvement

Verification and Validation

Managing Performance & Management

Continuity

Risk & Opportunity Management

Verified Answer
Correct Option - a