The CEO decides to change the terminology in Scrum to best fit their organization. What should the scrum master do?
Allow change of only the artifacts
Say NO - Scrum cannot have changed terms
Make sure the terms are consistent and change them Scrum does not focus on terminology
Explain that changing terms will cause confusion
To get all Infosys Certified Advanced Scrum Master Exam questions Join Telegram Group https://rebrand.ly/lex-telegram-236dee