The Last Lot Exact setting on the Lot Size tab of the material master is checked. The Lot size setting is fixed lot with 100 Ea. What will be the result of running a SAP_PP_002 heuristic in case the demand is 80 and in another case the demand is 144?
Receipts created will be for 100 Ea and 200 Ea respectively
Receipts created will be for 80 Ea and 200 Ea respectively
Receipts created will be for 100 Ea and 144 Ea respectively