The support activity carried out by Mark’s team follow a workflow that has a workstage ‘Compliance Confirmation’ with a WIP limit of 5. What does this mean?

There should be a minimum of 5 tasks under this workstage, at an instance of time

There should be exactly 5 tasks under this workstage, at an instance of time

There can be a maximum of 5 tasks under this workstage at an instance of time

There should be 5 team members attending to the tasks present under this workstage

Verified Answer
Correct Option - c