The work order WO1 requires only resource CNC4 to complete the manufacturing process. The efficiency of CNC4 is 80% and utilization is marked as 50% only. If 3 hours of work is required to be done using this resource for the work order WO1, what will be the total duration which the manufacturing scheduler should consider? Also note that, in between there will be a 30 min safety drill for workers which has already been marked as shift exception for that day.

7.5 Hours
8.0 Hours
37.5 Hours
8.5 Hours
Verified Answer
Correct Option - b