There are various levels of finite planning possible between fully finite and infinite planning. Finiteness Level indicates what amount / level of finite scheduling is to be done by PPDS
There is no such setting for finiteness level
It is used to decide which heuristics / profiles should do finite planning and which ones should do infinite planning based on the setting in the heuristics and in the resource
Finiteness level is only applied to the resource to indicate whether it is finite or infinite