Which one of the following statements is in-correct

Components that are reserved for Order 1 cannot be issued to Order 2
When a stock material is added in the components list of order, the system creates reservation
Operation number increment (default is 10) can be changed inside a order
One Order can have only one costing variant for planned costs
Verified Answer
Correct Option - a

To get all Infosys Certified SAP Plant Maintenance Professional Consultant Exam questions Join Telegram Group https://rebrand.ly/lex-telegram-236dee

Telegram