XYZ Inc. is facing a challenge. The development team has adopted an agile approach for rapid and incremental development. However, the operations team is unable to handle frequent releases as they need to plan for adequate testing, release checks, adequate knowledge transfer and for production support. The handover from development to operations team is also taking really long. Which of these issues will be resolved if XYZ decides to implement DevOps?

A: Delayed Time to Market

B: Deployment Delays

C: Prolonged Timelines for Service Assurance

Options A and B only
Options A and C only
Option B only
Options A, B and C only
Verified Answer
Correct Option - d

To get all Infosys Certified Agile Digital Technology Manager Exam questions Join Telegram Group https://rebrand.ly/lex-telegram-236dee

Telegram

We're passionate about offering best placement materials and courses!! A one stop place for Placement Materials. We daily post Offcampus updates and Placement Materials.

Qtr No. 213, New Town Yehlanka Indore 454775

admin@prepflix.in

Updated on Thu, 27 Nov 2025