You have done lot of changes to an Active planning area and now planning area activation is failing. You are not able to solve the error and backing out changes will take huge time and you need to bring the system up ASAP. What is most suitable course of action in this situation even if it is OK to delay the features you were providing as part of the changes?

You can restore planning area back to active instance

Raise Support Incident to SAP

Perform planning area copy from backup planning area

No option but finding all changes one by one and revert

Verified Answer
Correct Option - a